The Wind Turbine was installed in 2011.
The various sections of the wind turbine completed the journey from Lyness to Ore Brae and were assembled in situ.
Here are some photographs showing the various stages.
In order to take the left-hand turn from Lyness to Ore Brae required making a circular tour of the Hoy Hotel! Once up the hill and at the site the sections had to be lifted off the trucks and then be lifted on top of each other and secured into position.
Update Nov 2020
As this project has recently slipped into its tenth year of operation we thought it might be a good time to circulate an update as to the story so far, whilst also providing some insight as to some of the challenges that lay ahead. An amount of the information will already be well known to some community members, but has been included / repeated to benefit those who have joined us more recently.
The Island of Hoy Development Trust (IoHDT) started the project in 2008 and after early feasibility studies, and having identified a site, it obtained funding for initial project development alongside very similar projects on Eday, Shapinsay, Rousay and Stronsay.
The IoHDT immediately formed a trading subsidiary, Hoy Energy Ltd (HEL) and charged them with the task of obtaining capital funding and developing / completing the turbine project as modelled and allowing the targeted outcomes to be achieved.
In March 2011 HEL achieved closure on a £1.74m financial package with 90% funding from the Co-op Bank – repayable over 15 years. The €900k Enercon turbine was ordered from Germany and the £800k civil engineering works started in early May. The turbine went live and started generating to the Orkney distribution grid on October 20th 2011.
The turbine is an Enercon E44 which stands on a 45m tower, has a rotor blade diameter of 44m and measures 67m at its highest point. When generating at full power it produces 900kW and exports to grid at 11,000 volts.
In order to produce 900kW the turbine requires a steady wind speed of minimum 14m/s (32mph) which will allow it to spin at 33rpm under full blade pitch. If the wind speed exceeds 28m/s then the turbine automatically feathers its blades to a neutral angle and shuts down into storm mode. The relationship between wind speed and generation is more cubic than linear, so sadly if the wind speed drops 10% then output will drop nearer to 30%. Whilst the turbine does an excellent job of adapting to all wind speeds the days where a continuous 900kW output is achieved are indeed quite rare, often a brisk day will see the turbine churning merrily at 30rpm but will likely be only be producing around 500kW.
The annual production target in the financial model (used to obtain the bank loan) is 2,294,000 kW/h. To date we have managed to hit this target every year except for two, 2015 and 2019.
As the project qualified for a feed-in-tariff in 2011, a government generation subsidy, the income it obtains is proportionally higher than any current wind farm project could obtain as the FiT is now closed to new applications.
Our project sells all of its generated energy to the national grid via a power purchase agreement (PPA), currently with NPower, which generally achieves between 3p and 5p per kW/h dependent on market prices and seasonal trends. In addition we claim a FiT of 12.7p per kW/h, so total income is currently around 17p per unit, roughly the same as most of us pay for our domestic electricity.
Annually the project will generally gross between £370k and £450k, of course dependent entirely on wind levels as well as other factors such as breakdowns and export limitations from grid constraints. Due to the high levels of bank funding the project is subject to tight financial controls, managed quarterly by the Co-op Bank with formal accounting audits being completed annually by Scholes Accountants in Kirkwall.
HEL only receives money earned by the turbine from the bank (quarterly waterfall payments) when all pending loan payments have been made and various financial covenant tests have been passed.
HEL employs part time staff to operate and monitor the turbine on a 24/7 basis, as well as conducting the administrative tasks, covering everything from risk assessments and health and safety management through to organising maintenance and of course the all-important monthly energy sale and FiT claims.
The HEL management team consists of five directors, two of which are common to the IoHDT board. The team as a whole benefits from a wide range of experience in the social, commercial and technical arenas coupled with professional legal and financial expertise.
HEL does not pay bonuses or share dividends, with 100% of taxable profits being formally targeted for donation to the IoHDT, using the trusts charitable status to minimise corporation tax. Any amount of trading surplus not transferred to the trust is retained in HEL and formally accounted as an operational reserve in readiness to fund future repairs such as turbine blade replacement, the current operational reserve is £525k
All HEL and IoHDT audited accounts and financial statements are available in the public domain.
Income from HEL to the IoHDT was originally modelled to be around £75k pa starting in 2013, transfers actually started in 2012 and to date have averaged out at £90k pa. This money has been managed by the trust to achieve and maintain the initial project outcomes, which include the community bus service, refurbishment and support of the islands community centres and provision of a community benefit fund.
Information on the community benefit fund, including how it is managed and how awards are made is available from the IoHDT.
HEL have faced many challenges over the past 9 years, including extensive lightning damage on two occasions, extended periods of grid exclusion due to data communication issues and generator winding failures through salt corrosion being amongst the worst. Sub-sea cable failures have also been responsible for reduced income in the last 2 years, an issue that sadly has yet to be fully resolved.
More recently the HEL board are looking at strategies for the post year 12 period, when a prepaid / pre-budgeted service and repair contract (EPK) from Enercon will no longer be available – additionally worrying as Enercon are now looking to diversify their business away from on-shore wind turbines.
Financial provision is also required due to the expectation of blade replacement being required in the next few years, with a set of new blades currently sitting on the Enercon price list at circa €400k ex works, the final cost with shipping, crane mobilisation and engineers would likely see a final figure close to £500k. At the outset we were informed by Enercon that operational life expectancy for an E44 turbine was 18 years, but this could be less in Orkney due to high wind levels.
We are currently in year 10 and so in the not too distant future, probably after the post EPK year 12 situation is clear, the HEL board will be looking at options to hopefully replace the existing project and or exit in such a manner as to maximise community benefit. Hopefully the more recent IoHDT Legacy Project will make some headway towards that goal.
Should anyone want additional information please feel free to contact the IoHDT or any of the HEL Directors, or send an email to bclegg2008@gmail.com.
Turbine performance since it was commissioned:
The project has a targeted level of performance based on the turbine site wind yield report. Project financing from the main project funder was modelled using this report and target.
Achieving 100% of this target should comfortably allow projected operational costs to be met as well as provide a surplus for the community benefit fund.
Summer months will likely be below the mean target, hopefully winter months will be above!
Financial Year 2012/13
Yearly Summary: Turbine performance was 95% of target
Financial Year 2013/14:
Yearly Summary: Turbine performance was 118% of target
Monthly 2013/14
April 2013
May 2013
June 2013
July 2013
Aug 2013
Sep 2013
Oct 2013
Nov 2013
Dec 2013
Jan 2014
Feb 2014
Mar 2014
Turbine performance
105% of target
75% of target
49% of target
56% of target
63% of target
99% of target
120% of target
167% of target
182% of target
193% of target
166% of target
143% of target
Financial Year 2014/15:
Yearly Summary: Turbine performance was 70% of target (prior to loss adjustment)
Monthly 2014/15
April 2014
May 2014
June 2014
July 2014
Aug 2014
Sep 2014
Oct 2014
Nov 2014
Dec 2014
Jan 2015
Feb 2015
Mar 2015
Turbine performance
84% of target
28% of target
34% of target
45% of target
88% of target
49% of target
119% of target
121% of target
29% of target *
59% of target *
39% of target *
143% of target
* Storm damage
Financial Year 2015/16:
Yearly Summary: Turbine performance was 105% of target
Monthly 2015/16
April 2015
May 2015
June 2015
July 2015
Aug 2015
Sep 2015
Oct 2015
Nov 2015
Dec 2015
Jan 2016
Feb 2016
Mar 2016
Turbine performance
96% of target
121% of target
82% of target
64% of target
52% of target
78% of target
100% of target
140% of target
174% of target
153% of target
120% of target
77% of target
Financial Year 2016/17:
Yearly Summary: Turbine performance was 98% of target.
Monthly 2016/17
April 2016
May 2016
June 2016
July 2016
Aug 2016
Sep 2016
Oct 2016
Nov 2016
Dec 2016
Jan 2017
Feb 2017
Mar 2017
Turbine performance
101% of target
67% of target
50% of target
62% of target
70% of target
92% of target
105% of target
112% of target
115% of target
140% of target
139% of target
119% of target
Financial Year 2017/18:
Yearly Summary: Turbine performance was 111% of target.
Monthly 2017/18
April 2017
May 2017
June 2017
July 2017
Aug 2017
Sept 2017
Oct 2017
Nov 2017
Dec 2017
Jan 2018
Feb 2018
March 2018
Turbine performance
144% of target
58% of target
62% of target
61% of target
69% of target
98% of target
144% of target
175% of target
127% of target
130% of target
122% of target
136% of target
Financial Year 2018/19:
Yearly Summary: Turbine performance was 97% of target.
Monthly 2018/19
April 2018
May 2018
June 2018
July 2018
Aug 2018
Sept 2018
Oct 2018
Nov 2018
Dec 2018
Jan 2019
Feb 2019
March 2019
Turbine performance
69% of target
50% of target
71% of target
44% of target
56% of target
136% of target
151% of target
130% of target
133% of target
119% of target
89% of target
111% of target
Financial Year 2019/20:
Yearly Summary: Turbine performance was 98% of target.
Monthly 2019/20
April 2019
May 2019
June 2019
July 2019
August 2019
September 2019
October 2019
November 2019
December 2019
January 2020
February 2020
March 2020
Turbine performance
63% of target
54% of target
40% of target
24% of target
39% of target
108% of target
120% of target
110% of target
112% of target
197% of target
173% of target
132% of target
Financial Year 2020/21:
Yearly Summary: Turbine performance was 89% of target.
Monthly 2020/21
April 2020
May 2020
June 2020
July 2020
August 2020
September 2020
October 2020
November 2020
December 2020
January 2021
February 2021
March 2021
Turbine performance
64% of target
87% of target
49% of target
74% of target
33% of target
85% of target
87% of target
133% of target
140% of target
81% of target
116% of target
120% of target
Financial Year 2021/22:
Yearly Summary: Turbine performance was 86% of target.
Monthly 2021/22
April 2021
May 2021
June 2021
July 2021
Aug 2021
Sept 2021
Oct 2021
Nov 2021
Dec 2021
Jan 2022
Feb 2022
March 2022
Turbine performance
78% of target
57% of target
29% of target
37% of target
39% of target
59% of target
117% of target
125% of target
116% of target
85% of target
178% of target
117% of target
Financial Year 2022/23:
Yearly Summary: Turbine performance was 97% of target.
Monthly 2022/23
April 2022
May 2022
June 2022
July 2022
Aug 2022
Sept 2022
Oct 2022
Nov 2022
Dec 2022
Jan 2023
Feb 2023
March 2023
Turbine performance
76% of target
75% of target
80% of target
89% of target
47% of target
97% of target
131% of target
152% of target
120% of target
140% of target
82% of target
72% of target
Financial Year 2023/24:
Yearly Summary: Turbine performance was 96% of target.
Monthly 2023/24
April 2023
May 2023
June 2023
July 2023
August 2023
September 2023
October 2023
November 2023
December 2023
January 2024
February 2024
March 2024
Turbine performance
70% of target
79% of target
25% of target
55% of target
82% of target
82% of target
132% of target
88% of target
134% of target
163% of target
133% of target
110% of target
Financial Year 2024/25:
Yearly Summary: Turbine performance is currently 87% of target.
Monthly 2024/25
April 2024
May 2024
June 2024
July 2024
August 2024
September 2024
October 2024
November 2024
Turbine performance
130% of target
80% of target
107% of target
35% of target
74% of target
66% of target
110% of target
91% of target
Great plans for the future in Orkney