Turbine performance since it was commissioned
Financial Year 2012/13: Turbine performance was 95.32% of target
Financial Year 2013/14: Turbine performance was 118.17% of target
Monthly 2013/14:
- April 2013 Turbine performance was 105% of target
- May 2013 Turbine performance was 75% of target
- June 2013 Turbine performance was 49% of target
- July 2013 Turbine performance was 56% of target
- Aug 2013 Turbine performance was 63% of target
- Sept 2013 Turbine performance was 99% of target
- Oct 2013 Turbine performance was 120% of target
- Nov 2013 Turbine performance was 167% of target
- Dec 2013 Turbine performance was 182% of target
- Jan 2014 Turbine performance was 193% of target
- Feb 2014 Turbine performance was 166% of target
- Mar 2014 Turbine performance was 143% of target
Monthly 2014/15:
- Apr 2014 Turbine performance was 84% of target
- May 2014 Turbine performance was 28% of target
- June 2014 Turbine performance was 34% of target
- July 2014 Turbine performance was 45% of target
- Aug 2014 Turbine performance was 88% of target
- Sept 2014 Turbine performance was 49% of target
- Oct 2014 Turbine Performance was 119% of target
- Nov 2014 Turbine Performance was 121% of target
- Dec 2014 Turbine Performance was 29% of target
- Jan 2015 Turbine Performance was tbc% of target
The project has a targeted level of performance based on the turbine site wind yield report. Project financing from the main project funder was modelled using this report and target.
Achieving 100% of this target should comfortably allow projected operational costs to be met as well as provide a surplus for the community benefit fund.
Summer months will likely be below the mean target, hopefully winter months will be above!